CS 406 Software Engineering I
Fall 1999 Course Schedule


Week 1: Done 8/23 - 8/27 Week 9*Done 10/18 - 10/22
Week 2: Done 8/30-9/3 Week 10* Done 10/25 - 10/29
Week 3: Done 9/6 - 9/10 Week 11*Done 11/1 - 11/5
Week 4*:Done 9/13 - 9/17 Week 12*Done 11/8 - 11/12
Week 5*:Done 9/20 - 9/24 Week 13*Done 11/15 - 11/19
Week 6*:Done 9/27 - 10/1 Week 14 Done 11/22 - 11/26
Week 7: Midterm :Done 10/4 - 10/8 Week 15Done 11/29 - 12/3
Week 8:Done 10/11 - 10/15 Week 16* Done 12/6 - 12/10
Week 17<---Current 12/16:
Final Exam 7-9pm BCHM 105
                                                         *Video conference takes place during this week. NO video conference in unmarked weeks.
Back to CS 406 Homepage                                                         Revised: December 12, 1999

SRS: Textbook.     PSRS: Problems in the Textbook.    HW: Homework. TBA: Tool Based Assignment.
    UML: Readings from Recommended text or slides accessible via the Textbook page.
 

Date
Topic
Comments
T 8/24 Course Introduction: Mathur
Project Descriptions
Company representatives:
Robert A Byrne, Jr., Boeing
Steven Sutton, Tektronix
Th 8/26 Project Descriptions
Team formation: Mathur

Company representatives:
Eric Wiegman, Tellabs.
Brad Graves, Tivoli
Date Topic Comments
T 8/31 The What and Why of SE?: Mathur SRS: Chapter 1
Th 9/2 Software process: Mathur SRS: Chapters 2, 3
Date Topic Comments
T 9/7 Analysis-1: Murthy SRS Chapter 11,  UML: Chapters 1 and 4
Th 9/9 Analysis-2: Murthy SRS Chapter 11,  UML: Chapters 1 and 4
Date Topic Comments
T 9/14 Analysis-3: Murthy SRS Chapter 11, UML Chapters 5, 6, and 13.
Th 9/16 Project Progress 1 Video Conferencing
Date Topic Comments
T 9/21 Design-1 Murthy SRS Chapter 12, UML Chapter 16 
Th 9/23 Project Progress 2 Video Conferencing
Date Topic Comments
T 9/28 Design-2 Murthy SRS Chapter 12, UML Chapter 17
Th 9/30 Project Progress 3 Video Conferencing
Date Topic Comments
T 10/5 Design 3 and Review: Murthy SRS Chapter 12, UML Chapters 18 and 19.
Th 10/7 Midterm: 7--8:15pm BIOCHEM 105
THE 3pm CLASS WILL NOT MEET TODAY.
All topics covered until now, including  those covered through homeworks and laboratory assignments. If you have doubts about whether or not a topic was covered, see the analysis and design slides that were flipped during lectures. All slides are available through this site.
Date Topic Comments
T 10/12 October Break: No Class.
Th 10/14 Design 4: Murthy SRS Chapter 12, UML Chapters 19 and 20
Date Topic Comments
T 10/19 Design 5: Murthy SRS Chapter 12, UML Chapters 21 and 29.
Th 10/21 Project Progress 4A Video Conferencing.
Date Topic Comments
T 10/26 SCM: Ghosh  SRS Chapter 4.13-4.15
Th 10/28 Project Progress 4B Video Conferencing
Date Topic Comments
T 11/2 Testing-1: Ghosh Preliminaries
Th 11/4 Project Progress 5A: Video Conferencing
Date Topic Comments
T 11/9 Testing-2:Ghosh Functional testing, SRS Chapter 5 (excluding 5.5), Chapter 13.6-13.8
Th 11/11 Project Progress 5B Video Conferencing
Date Topic Comments
T 11/16 Testing-3: Ghosh Adequacy measurement and SRS Chapter 13.6-13.8
Th 11/18 Project Progress 6 Video Conferencing
Date Topic Comments
T 11/23 Testing 4: Ghosh Adequacy measurement continued
Th 11/25 Thanksgiving: No Class.
Date Topic Comments
T 11/30 Metrics: Ghosh SRS from different chapters
Th 12/2 Course Review: Mathur Prepare for the final demo and polish your report!
Date Topic Comments
T 12/7 Prototype demo Video Conferencing
Th 12/9 Prototype demo Video Conferencing
Date Topic Comments
Th 12/16 Final Exam : 7-9pm BCHM 105 This will be a comprehensive exam. (Approximate percentages given below.)
Config management: 10 points
Metrics: 10 points
Testing: 55
UML (post midterm): 15
Miscellaneous: 10

Total: 100

Back to CS 406 Homepage