CS 406
Software Engineering I
Fall 1999
Course Schedule
Week 1: Done | 8/23 - 8/27 | Week 9*Done | 10/18 - 10/22 |
Week 2: Done | 8/30-9/3 | Week 10* Done | 10/25 - 10/29 |
Week 3: Done | 9/6 - 9/10 | Week 11*Done | 11/1 - 11/5 |
Week 4*:Done | 9/13 - 9/17 | Week 12*Done | 11/8 - 11/12 |
Week 5*:Done | 9/20 - 9/24 | Week 13*Done | 11/15 - 11/19 |
Week 6*:Done | 9/27 - 10/1 | Week 14 Done | 11/22 - 11/26 |
Week 7: Midterm :Done | 10/4 - 10/8 | Week 15Done | 11/29 - 12/3 |
Week 8:Done | 10/11 - 10/15 | Week 16* Done | 12/6 - 12/10 |
Week 17<--- | 12/16:
|
SRS: Textbook.
PSRS: Problems in the Textbook. HW: Homework.
TBA: Tool Based Assignment.
UML: Readings from Recommended text or slides accessible
via the Textbook page.
|
|
|
T 8/24 | Course
Introduction: Mathur
Project Descriptions |
Company
representatives:
Robert A Byrne, Jr., Boeing Steven Sutton, Tektronix |
Th 8/26 | Project
Descriptions
Team formation: Mathur |
Company representatives: Eric Wiegman, Tellabs. Brad Graves, Tivoli |
Date | Topic | Comments |
T 8/31 | The What and Why of SE?: Mathur | SRS: Chapter 1 |
Th 9/2 | Software process: Mathur | SRS: Chapters 2, 3 |
Date | Topic | Comments |
T 9/7 | Analysis-1: Murthy | SRS Chapter 11, UML: Chapters 1 and 4 |
Th 9/9 | Analysis-2: Murthy | SRS Chapter 11, UML: Chapters 1 and 4 |
Date | Topic | Comments |
T 9/14 | Analysis-3: Murthy | SRS Chapter 11, UML Chapters 5, 6, and 13. |
Th 9/16 | Project Progress 1 | Video Conferencing |
Date | Topic | Comments |
T 9/21 | Design-1 Murthy | SRS Chapter 12, UML Chapter 16 |
Th 9/23 | Project Progress 2 | Video Conferencing |
Date | Topic | Comments |
T 9/28 | Design-2 Murthy | SRS Chapter 12, UML Chapter 17 |
Th 9/30 | Project Progress 3 | Video Conferencing |
Date | Topic | Comments |
T 10/5 | Design 3 and Review: Murthy | SRS Chapter 12, UML Chapters 18 and 19. |
Th 10/7 | Midterm:
7--8:15pm BIOCHEM 105
THE 3pm CLASS WILL MEET TODAY. |
All topics covered until now, including those covered through homeworks and laboratory assignments. If you have doubts about whether or not a topic was covered, see the analysis and design slides that were flipped during lectures. All slides are available through this site. |
Date | Topic | Comments |
T 10/12 | October Break: No Class. | |
Th 10/14 | Design 4: Murthy | SRS Chapter 12, UML Chapters 19 and 20 |
Date | Topic | Comments |
T 10/19 | Design 5: Murthy | SRS Chapter 12, UML Chapters 21 and 29. |
Th 10/21 | Project Progress 4A | Video Conferencing. |
Date | Topic | Comments |
T 10/26 | SCM: Ghosh | SRS Chapter 4.13-4.15 |
Th 10/28 | Project Progress 4B | Video Conferencing |
Date | Topic | Comments |
T 11/2 | Testing-1: Ghosh | Preliminaries |
Th 11/4 | Project Progress 5A: | Video Conferencing |
Date | Topic | Comments |
T 11/9 | Testing-2:Ghosh | Functional testing, SRS Chapter 5 (excluding 5.5), Chapter 13.6-13.8 |
Th 11/11 | Project Progress 5B | Video Conferencing |
Date | Topic | Comments |
T 11/16 | Testing-3: Ghosh | Adequacy measurement and SRS Chapter 13.6-13.8 |
Th 11/18 | Project Progress 6 | Video Conferencing |
Date | Topic | Comments |
T 11/23 | Testing 4: Ghosh | Adequacy measurement continued |
Th 11/25 | Thanksgiving: No Class. | |
Date | Topic | Comments |
T 11/30 | Metrics: Ghosh | SRS from different chapters |
Th 12/2 | Course Review: Mathur | Prepare for the final demo and polish your report! |
Date | Topic | Comments |
T 12/7 | Prototype demo | Video Conferencing |
Th 12/9 | Prototype demo | Video Conferencing |
Date | Topic | Comments |
Th 12/16 | Final Exam : 7-9pm BCHM 105 | This will be a comprehensive exam. (Approximate percentages given below.)
Config management: 10 points Metrics: 10 points Testing: 55 UML (post midterm): 15 Miscellaneous: 10 Total: 100 |