Day/Date
|
Topic
|
Comments
|
|
|
Last update: 6/25/98 |
Th
9/10 |
Project
Progress 1 |
Requirements:
Tellabs project. |
Th
9/17 |
Project
Progress 2 |
Requirements:
Tivoli project. |
Th
9/24 |
Project
Progress 3 |
Design
I: Tellabs project. |
Th
10/1 |
Project
Progress 4 |
Design
I: Tivoli project. |
Th
10/8, 10/15
|
No
presentations
|
Midterm
Examination and October Break
|
Th
10/22 |
Project
Progress 5 |
Design
II: Tellabs project. |
Th
10/29 |
Project
Progress 6 |
Design
II: Tivoli project. |
Th
11/5 |
Project
Progress 7 |
Design
III: Tellabs project. |
Th
11/12 |
Project
Progress 8 |
Design
III: Tivoli project. |
Th
11/19 |
Project
Progress 9 |
Prototype
I,II: Tellabs and Tivoli projects. |
T
11/24 |
Project
Progress 10 |
Prototype
preview: Tellabs and Tivoli projects. |
Th 11/26 |
No
presentations
|
Thanksgiving
Break
|
Th 12/3 |
No
presentations
|
Prepare for the final demo!
|
Th
12/10 |
Project
Progress 11 |
Prototype
demos: Tellabs and Tivoli projects. |