CS 406 Software Engineering 
Fall 1997 Team Project Presentation (Revised) Schedule 
 
Day/Date  
Topic  
Comments  
     Last  update: 11/10/97
M 9/8 Project Progress 1 Requirements: Tellabs project.
M 9/15 Project Progress 2 Requirements: Intel project.
M 9/22 Project Progress 3 Design I: Tellabs project.
M 9/29 Project Progress 4 Design I: Intel project.
W 10/8 Project Progress 5 Design II: Tellabs project.
M 10/20 Project Progress 6 Design II: Intel project.
W 10/29 Project Progress 7 Design III: Tellabs project.
W 11/5 Project Progress 8 Design III: Intel project.
W 11/12 Project Progress 9 Prototype I,II: Tellabs project.
W 11/19 Project Progress 10 Prototype I, II: Intel project.
M 11/24 Project Progress 11 Prototype preview: Tellabs project.
F 12/5  Project Progress 12 Prototype preview: Intel project.
F 12/12 Prototype demo All groups.
Back to Schedule
Back to CS 406 Homepage